Walcha High Country Guardians, Protect the Valley, Rouchel Brook Action Group and Voice for Walcha jointly object to the New England REZ Transmission Project

Our four community groups have combined local knowledge, landholder evidence and professional expertise from Walcha, the New England and the Upper Hunter to examine its consequences for the communities, industries and environments along the proposed corridor.

EnergyCo proposes a transmission network with 6 GW of transfer capacity linking New England to the existing grid at Bayswater. It includes approximately 305 kilometres of transmission corridor, five energy hubs, access roads, workforce camps and associated construction facilities. Its full consequences must be assessed together with the generation it is intended to support.

The Environmental Impact Statement (EIS) provides nowhere near enough detail for meaningful public scrutiny or a sound approval decision. Essential surveys, water supplies, construction arrangements, property impacts and safeguards remain incomplete or deferred. Some exhibited designs are already superseded. A promise to resolve these matters after approval cannot substitute for assessment before the decision.

The biodiversity impacts alone justify rejection. Extensive native vegetation clearing, habitat fragmentation and the risk of serious and irreversible harm to threatened species and ecological communities are unacceptable. Incomplete surveys and unresolved offset arrangements provide no sound basis for accepting those losses.

The impacts on agriculture and the Upper Hunter equine industry provide a further decisive ground for rejection. Farm fragmentation, restrictions on aerial operations, erosion, anthrax and other biosecurity risks, and disruption to breeding enterprises threaten productive capacity and business viability. These consequences extend beyond tower sites and easements to whole properties, connected businesses and regional industries.

Water security remains unresolved. The EIS has not established where sufficient, reliable water supplies will come from or how existing users will be protected. If assumed sources prove unavailable, replacement supplies can delay construction, require additional cartage over longer distances, increase road damage and intensify pressure on towns, agriculture and other water users. These consequences must be assessed before approval.

The project must demonstrate an overall net benefit to NSW, accounting for its full financial, environmental and community costs. With households and businesses facing cost of living pressure, value for electricity consumers must be established. Changes (reductions) in the generation pipeline, increasing transmission costs and network assumptions require independent scrutiny, alongside a fair comparison with energy and network alternatives that may deliver greater public benefit at lower cost. Where there are better options, they must be considered.

Constructability must be assessed across the whole project. The EIS has not demonstrated that steep terrain, weather and bushfire restrictions, roads, water, quarry materials, specialist equipment and workforce requirements can be managed together to deliver the project within a credible budget and an acceptable timeframe. Each of these risks can compound and multiply the impact on the other. This accumulation of impacts has not been considered or assessed. Unresolved delivery risks expose communities to prolonged disruption and additional costs.

The submission also identifies serious concerns for cultural and historical heritage, water security, public health, roads, tourism and essential services. The combined demands of the wider REZ, and responsibility for rehabilitation, waste and future liabilities, remain inadequately resolved. Communities and councils must not be left to absorb those consequences.

These impacts cannot be assessed in silos. Agriculture, for example, is exposed simultaneously to water pressures, transport disruption and labour shortages. A failure in any assumed supply of water, materials or workers can delay the whole project and prolong these pressures on businesses, communities and industries. The impacts accumulate and multiply as one constraint worsens another. Their combined harm can exceed the sum of the individual impacts. The assessment must examine these interactions, including how delays extend the duration and severity of disruption.

These are fundamental objections to the project's location, scale, impacts and justification. They cannot be answered by assurances, future management plans or conditions that leave essential questions unresolved.

Taken together, the evidence establishes that this project should be rejected.